Lea Marshes   Basketball project

 

Sandy Path mud bath   

                                                                                    (Photos Karl Weiss June 13, 2012).
Condition 11 of the LBWF planning application that allowed the ODA to build on the urban equivalent of green belt (Metropolitan Open Land) was: "11.Prior to the commencement of the development, a Construction Method Statement detailing measures to meet the ODA Code of Construction Practice (2007) , including details of wheel washing facilities for vehicles leaving the site during construction works shall be submitted to and approved by the Local Planning Authority. A similar Method Statement shall thereafter be submitted relating to the removal of the buildings prior to commencement of removal of the facilities. All works shall thereafter be carried out in strict compliance with the agreed details."
Path reinstated December 2012